Tempe Sign Permit Guide for Small Business Owners

November 18, 2026

If you are putting up a new wall sign, monument sign or banner in Tempe, you almost certainly need a sign permit. The City of Tempe requires one for all new building-mounted and free-standing signs. The application goes through the city’s online portal, and a licensed sign contractor has to file it. Your part comes first: a sign design with exact dimensions, colors and materials that you settle before anyone files anything.

This guide covers what needs a permit, what is exempt, what it costs, how the process runs and where applications go wrong. It is written for owners, not for sign installers.

Charles-creative
Make Your Sign Match Your Brand
Charles-creative creates custom branding and website design for small businesses, helping your visual identity feel clean, modern, and established.

TL;DR

  • Tempe requires a permit for new building-mounted and free-standing signs, and for any change to an existing sign’s face, copy, colors or supports, except routine maintenance.
  • A licensed Arizona sign contractor with an active CR-38 license submits the application online through the Tempe Citizen Access Portal.
  • Fees are set per fiscal year (July 1 to June 30). The city’s signs page lists $368 for one sign and $140 for each additional sign, and it publishes first review at 6 to 10 business days.
  • Window signs, small portable signs and a few other types do not need a permit, but they have size and placement limits.
  • Finalize your artwork, dimensions and materials before you apply. Changes after submittal mean resubmittals and lost time.

Table of Contents

Which signs need a Tempe permit

The city’s sign code says a permit is needed to erect, install, relocate, modify or change any sign. “Modify” is broader than most owners expect. It covers any change to an existing sign’s face, copy, colors or supporting structure. Only maintenance is excluded.

In practice, that means:

  • Wall or building-mounted signs: channel letters, cabinet signs, blade signs.
  • Free-standing signs: monument signs and pylon-style signs.
  • Banners and similar temporary displays: pennants, streamers, balloons and inflatables (the city calls these Type K).
  • Rebrands on existing signs: a new logo or new colors on an existing cabinet is a modification.
  • Illuminated signs: these also need to meet the electrical code. Address signs are the exception.

The city’s Signs page also links a Sign Permit Submittal Checklist. Read it before you commission a design, because it lists the full scope of work that needs a permit.

What does not need a permit

Some signs skip the permit, but they still have limits. According to the city’s sign code, no permit is needed for window signs, limited to 25% of the window area. The same table exempts these:

  • Commercial portable signs placed within 3 feet of the building (Type Q). They are limited to 5 feet in height and 8 square feet, one per tenant frontage, and may be out only from 6 a.m. to 9 p.m.
  • Vacancy signs (Type R), limited to 8 feet in height and 6 square feet, one per frontage.
  • Signs attached to fuel dispensing pumps (Type I), up to 3 square feet.
  • Right-of-way signs, only where state law authorizes them.

Traffic and other governmental street signs and public utility safety signs are fully exempt from the code.

No permit does not mean no rules. A sandwich board that is too big or sits outside the 3-foot zone can draw a code violation even though you never needed a permit for it.

Temporary signs and banners

Banners are where owners most often get caught. Type K signs need a permit, and the allowed time is limited. A new business gets one 30-day Type K sign, one time only. Every other business gets 21 cumulative days per six-month period in a calendar year.

Type K banner time limits by business category

So plan your banner for the moment it matters. A grand opening banner used up on a slow week is gone. Many owners want a banner for a sale and then another for a promotion, and the 21-day cap means you have to choose.

Construction and undeveloped-land signs follow separate rules. A construction site sign (Type J) must be attached to a temporary construction fence, can be no taller than 8 feet, and is allowed only from building permit issuance until the final certificate of occupancy. A sign on undeveloped property (Type L) is limited to 8 feet in height and 32 square feet, one per street frontage, and can stay for 12 months until the certificate of occupancy arrives.

Free-standing sign limits to design around

If you want a monument sign, the dimensions are not a suggestion. The city’s free-standing sign code sets these limits for Type D, the common multi-tenant monument:

Parcel and tenants Max sign area Panels Max height
Up to 4 tenants, parcel under 5 acres 24 sq ft 4 8 ft
More than 4 tenants, parcel under 5 acres 40 sq ft 6 8 ft
Parcel over 5 acres 40 sq ft 6 10 ft

Other rules apply too. You get one sign per street frontage or per 300 feet of frontage. The sign needs a masonry monument base and address numerals at least 6 inches tall. The building-safety page adds that free-standing signs have no setback requirement, but cannot sit in an easement or the public right-of-way and must respect the clear vision triangle, the corner area drivers need to see through.

Smaller categories exist as well. Type C, within 5 feet of a drive-through, allows a 45 square foot face at up to 8 feet high. Type F covers theatres, museums, service stations and places of worship with no residential use. Type E, near the freeway, needs a City Council Development Agreement. Most small businesses will not touch these, so confirm yours with the city before you spend on design.

Do you need a sign package?

If you lease space in a shopping center, your sign may already be governed by something larger than the sign code. The city requires a Sign Package for all developments in mixed-use (MU-X) districts, commercial centers with more than one tenant, and single-tenant buildings converted to house additional tenants. Your sign has to match the approved package or get approval for a deviation.

Tenant signs aligned across a Tempe center

Creating or amending a package takes a Sign Development Plan Review application through the Permit Center, with a $553 fee listed on the city’s page. Before you design anything, ask your landlord for the center’s approved sign criteria. Many rejected designs fail because they ignored the center’s own rules, not the city’s.

How the application works

The process, step by step:

  1. Check the rules for your sign type and location. Use the sections above and the city’s checklist. This is also when you confirm whether a sign package applies.
  2. Finalize the design. You need the sign’s face, copy, colors, dimensions and materials locked. This is the step you control most.
  3. Hire a licensed sign contractor. Under Arizona rules (A.A.C. R4-9-104), the application must be submitted by an Arizona licensed sign contractor with an active CR-38 license. Getting the permit is not a do-it-yourself job, even for a banner.
  4. Get owner authorization. If you are a tenant, the application needs a Property Owner Authorization from the landlord.
  5. Contractor submits online. Filing happens in the Citizen Access Portal (New, then Planning/Signs, then Planning, then Sign Permit). Questions can go to the Permit Center at 480-350-4311 or permitcenter@tempe.gov.
  6. Review, inspection, install. The fee covers plan review, the initial field inspection and one re-inspection.

What the submittal includes

The city asks for a site plan, elevations, details (materials, colors, electrical specs, mounting), and sections or cross-sections. The sign code adds two scale drawings with dimensions and area calculations, a development plan showing sign locations, illumination and shielding details, and contact information. Structural calculations are required for free-standing signs over 8 feet and building-mounted signs projecting more than 16 inches. Electrical work must meet the National Electrical Code.

Your contractor prepares the engineering. What you supply is the brand side: logo files, exact colors, letter styles, the copy and the layout. Clean, final artwork keeps the drawings accurate.

Fees and timing

Fees reset each fiscal year on July 1, and the city has published slightly different figures at different points, so treat any number as the figure for its period. The city’s signs page lists these fees for the fiscal year:

Item Fee listed on the city’s signs page
One sign $368
Each additional sign $140
Type K (Grand Opening, Significant Event) $184
Sign Package $553
Unauthorized installation Twice the normal fee

The city’s fee schedule effective July 1, 2025 lists $378 for one sign, $143 for each additional sign and $189 for Type K permits and leasing banners, and it adds $41 for a Type Q way-finding sign permit. The numbers shift year to year, so confirm the current amount with the Permit Center before you budget. Your contractor will also charge for engineering, drawings and installation, which is separate from the city fee.

The city’s page lists first review at 6 to 10 business days and resubmittals at 3 to 5 business days. A design change after submittal can push you back into that second round, so count on a few weeks from filing to install, and longer if you need corrections.

The unauthorized installation penalty is the number to remember. Putting a sign up first and asking later doubles the fee.

Recent procedure changes

Tempe updated its planning side recently. The Tempe Independent reported in December 2025 that the Planning Division refreshed its online applications, forms and permits, with new checklist contents and document naming requirements. It also reported that starting December 31, 2025, Development Plan Review and Subdivision applications are decided by staff instead of at public meetings, following Arizona House Bill 2447. Submittal deadlines stay Monday by 5 p.m.

For a sign owner, the practical point is simple: download the current checklist and form names from the city’s page each time, not from an old file your contractor used last year.

Where applications go wrong

These are the usual slip-ups, drawn from the rules above:

  • Treating a rebrand as maintenance. A new face, copy or color scheme is a modification and needs a permit.
  • Ignoring the center’s sign package. The city requires conformance with an approved package.
  • Oversized monument panels. Check the 24 and 40 square foot limits, and the height cap for your parcel.
  • Forgetting the base and numerals. Free-standing signs need a masonry base and 6-inch address numerals on both sides.
  • Burning your banner days. Type K time is capped.
  • Missing owner authorization. Tenants need the landlord’s sign-off.
  • Late artwork changes. Every revision after submittal risks another review cycle.

Address numbers are a small point with a real rule. The city’s permanent sign page says they must be at least 4 inches tall with at least 50% color contrast, and lit from dusk to dawn in most commercial cases.

Designing a sign that clears review and works

A permit tells you what is allowed. It does not tell you what will be read from a car at 35 miles per hour. Because Tempe caps your area, every square foot has to do work: fewer words, strong contrast, one clear logo. Our guide to signage design guidelines for small business walks through letter size, contrast and layout so you do not pay for a reprint.

If you also run in Phoenix, the rules and fees differ, and we cover them in our Phoenix sign permit guide. When your files go to a fabricator or printer, a print-ready files checklist saves another round of corrections.

Our point of view

Most owners come to us after the sign is already built, and the logo on it was never designed for a sign. It was designed for a business card and stretched.

We build every project bespoke, with no templates, and you work directly with me from start to finish. That matters for signage because the sign is the one place where your brand has to survive a hard limit on size, a fixed color list and a driver’s three-second glance.

You also own every asset we create, with no licensing fees and no vendor lock-in. When your sign contractor asks for vector files, exact colors and letter styles, you hand them over and you are done. Nobody has to ask us for permission.

Start with the brand, then the sign. A strategy-led identity makes permit drawings easier, because the decisions are already made.

Charles

Get the brand side of your sign ready

We design the identity and the signage artwork your contractor will build from. Our Print & Collateral service covers business cards, flyers and signage for small businesses, and our Brand & Identity work gives you the logo, colors and guidelines that keep every sign consistent. You work directly with the creative director, and you own what we make.

Charles-creative

If you are planning a new sign or a rebrand, contact us before you hire the sign contractor. A finished design means a cleaner application.

FAQ

Can I apply for a Tempe sign permit myself?

No. Tempe’s signs page says applications must be submitted by an Arizona licensed sign contractor with an active CR-38 license, under state rules. As the owner, you supply the design, the landlord authorization if you rent, and the decisions about size and placement. The contractor files and manages the permit.

Do I need a permit to change the logo on my existing sign?

Usually yes. The sign code defines modifying a sign as any change to its face, copy, colors or supporting structure, with only maintenance excluded. A new logo on an existing cabinet falls under that definition. Confirm with the Permit Center at 480-350-4311 if your change is minor.

Do I need a permit for a window sign or a sandwich board?

Not for window signs up to 25% of the window area, and not for a commercial portable sign within 3 feet of the building that is no more than 5 feet tall and 8 square feet, one per tenant frontage, displayed 6 a.m. to 9 p.m. Exceeding those limits can bring a violation.

How long does Tempe take to review a sign permit?

The city lists 6 to 10 business days for first review and 3 to 5 business days for resubmittals. The fee includes plan review, the initial field inspection and one re-inspection. Incomplete drawings or late design changes are the common reasons for a second round.

What happens if I install a sign without a permit?

The city charges twice the normal permit fee for unauthorized installation. You still have to go through the permit process, so the sign can end up costing more and taking longer than if you had filed first.